CUP: C81H11000150001
LAVORI DI RICOSTRUZIONE IMMOBILI PRIVATI IN CLASSE DI PRIORIT AAA PEU 22 SP 5
SUMMARY OF THE PROJECT
LAVORI DI RICOSTRUZIONE IMMOBILI PRIVATI IN CLASSE DI PRIORIT AAA PEU 22 SP 5
Implementation indicator
Volume oggetto di intervento
- Target
- 5,017.19 mc
- Achieved
- 5,017.19 mc
Download project
Funding monitored
€ 841,345.23
of which cohesion funds
€ 841,345.23
Given name | Amount |
---|---|
Development and Cohesion Fund | 841345.23 |
- Economies:
- € 0.06
Payments monitored
€ 841,345.23
of which cohesion funds
€ 841,345.23
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2016 | 50158.50 | 50158.50 | 5 |
2017 | 306502.04 | 356660.54 | 42 |
2018 | 314034.25 | 670694.79 | 79 |
2019 | 84670.06 | 755364.85 | 89 |
2020 | 85980.38 | 841345.23 | 100 |
State of progress
Completed
Expected start: 23/10/2015
Effective start: 23/10/2015
Expected end: 18/10/2019
Effective end: 18/10/2019
Entities
- Planning body
- REGIONE MOLISE
- Implementing body
- COMUNE DI URURI
- Beneficiary
- CONSORZIO PEU 22 (COMUNE DI URURI)
Programming area
- Programme
- PSC REGIONE MOLISE
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 841,345.23
- Payments on cohesion funds
- € 841,345.23
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico