CUP: D53G09000310001
LAVORI DI RICOSTRUZIONE IMMOBILI PRIVATI IN CLASSE DI PRIORIT AAA PEU 19 SP 1
SUMMARY OF THE PROJECT
LAVORI DI RICOSTRUZIONE IMMOBILI PRIVATI IN CLASSE DI PRIORIT AAA PEU 19 SP 1
Implementation indicator
Volume oggetto di intervento
- Target
- 1,120 mc
- Achieved
- 1,120 mc
Funding monitored
€ 138,347.10
of which cohesion funds
€ 138,347.10
Given name | Amount |
---|---|
Development and Cohesion Fund | 138347.10 |
- Economies:
- € 25,926.02
Payments monitored
€ 138,347.10
of which cohesion funds
€ 138,347.10
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2015 | 11856.20 | 11856.20 | 8 |
2016 | 0 | 11856.20 | 8 |
2017 | 111742.40 | 123598.60 | 89 |
2018 | 0 | 123598.60 | 89 |
2019 | 12293.80 | 135892.40 | 98 |
2020 | 2454.70 | 138347.10 | 100 |
State of progress
Completed
Expected start: 06/11/2015
Effective start: 06/11/2015
Expected end: 28/12/2017
Effective end: 28/12/2017
Entities
- Planning body
- REGIONE MOLISE
- Implementing body
- COMUNE DI CAMPODIPIETRA
- Beneficiary
- COMUNE DI CAMPODIPIETRA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE MOLISE
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico