CUP: J57H11001550002
Intervento di messa in sicurezza strade interne al capoluogo e frazioni
SUMMARY OF THE PROJECT
Intervento di messa in sicurezza strade interne al capoluogo e frazioni
Implementation indicator
Estensione in lunghezza
- Target
- 2.41 km
- Achieved
- 2.41 km
Download project
Funding monitored
€ 605,840.78
of which cohesion funds
€ 605,840.78
Given name | Amount |
---|---|
Development and Cohesion Fund | 605840.78 |
- Economies:
- € 65,159.22
Payments monitored
€ 598,757.61
of which cohesion funds
€ 598,757.61
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2016 | 262963.64 | 262963.64 | 43 |
2017 | 0 | 262963.64 | 43 |
2018 | 327906.84 | 590870.48 | 97 |
2019 | 10.50 | 590880.98 | 97 |
2020 | 0 | 590880.98 | 97 |
2021 | 7876.63 | 598757.61 | 98 |
State of progress
Completed
Expected start: 26/05/2014
Effective start: 26/05/2014
Expected end: 09/09/2017
Effective end: 07/09/2017
Entities
- Planning body
- REGIONE MOLISE, GIUNTA REGIONALE
- Implementing body
- COMUNE DI ISERNIA
- Beneficiary
- COMUNE DI ISERNIA
- Executor
- Tecnoscavi S.R.L.
Programming area
- Programme
- PSC REGIONE MOLISE
- Fondo Aree Sottoutilizzate 2000-2006
- 2000-2006 Underutilized Areas Fund
- Cohesion funds
- € 605,840.78
- Payments on cohesion funds
- € 598,757.61
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale