CUP: E91B03000060001
OPERE DI RIQUALIFICAZIONE DI CORSO BELVEDERE, VIA DUOMO E SEGRATO DELLA CHIESA
SUMMARY OF THE PROJECT
OPERE DI RIQUALIFICAZIONE DI CORSO BELVEDERE, VIA DUOMO E SEGRATO DELLA CHIESA
Implementation indicator
Non richesto (Migrazione PSC)
- Target
- 0.01 num
- Achieved
- 0.01 num
Funding monitored
€ 100,000.00
of which cohesion funds
€ 100,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 100000.00 |
Payments monitored
€ 100,000.00
of which cohesion funds
€ 100,000.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2005 | 19000.00 | 19000.00 | 19 |
2006 | 39155.62 | 58155.62 | 58 |
2007 | 41844.38 | 100000.00 | 100 |
State of progress
Completed
Expected start: 01/12/2005
Effective start: 01/12/2005
Expected end: 03/01/2007
Effective end: 03/01/2007
Entities
- Planning body
- REGIONE MOLISE
- Implementing body
- COMUNE DI MIRANDA
- Beneficiary
- COMUNE DI MIRANDA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE MOLISE
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale