CUP: G27D06000050001
REALIZZAZIONE DEL COLLEGAMENTO FOGNARIO IMPIANTO DI DEPURAZIONE
SUMMARY OF THE PROJECT
REALIZZAZIONE DEL COLLEGAMENTO FOGNARIO IMPIANTO DI DEPURAZIONE
Implementation indicator
Non richesto (Migrazione PSC)
- Target
- 0.01 num
- Achieved
- 0.01 num
Download project
Funding monitored
€ 686,910.53
of which cohesion funds
€ 686,910.53
Given name | Amount |
---|---|
Development and Cohesion Fund | 686910.53 |
- Economies:
- € 5,895.60
Payments monitored
€ 686,910.53
of which cohesion funds
€ 686,910.53
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2010 | 12573.85 | 12573.85 | 1 |
2011 | 386728.37 | 399302.22 | 58 |
2012 | 170553.92 | 569856.14 | 82 |
2013 | 111531.95 | 681388.09 | 99 |
2014 | 5522.44 | 686910.53 | 100 |
State of progress
Completed
Expected start: 10/03/2011
Effective start: 10/03/2011
Expected end: 31/05/2012
Effective end: 27/05/2012
Entities
- Planning body
- REGIONE MOLISE, GIUNTA REGIONALE
- Implementing body
- CONSORZIO DI SVILUPPO INDUSTRIALE ISERNIA-VENAFRO
- Beneficiary
- REGIONE MOLISE, GIUNTA REGIONALE
- Executor
- Melfi SRL
Programming area
- Programme
- PSC REGIONE MOLISE
- Fondo Aree Sottoutilizzate 2000-2006
- 2000-2006 Underutilized Areas Fund
- Cohesion funds
- € 686,910.53
- Payments on cohesion funds
- € 686,910.53
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Risorse idriche