CUP: D73H19000900006
Realizzazione nuovo edificio scolastico destinato a scuola elementare e materna G. Galilei
SUMMARY OF THE PROJECT
Realizzazione nuovo edificio scolastico destinato a scuola elementare e materna G. Galilei
Implementation indicator
Superficie oggetto di intervento
- Target
- 3,000 mq
- Achieved
- 0 mq
Download project
Funding monitored
€ 1,775,000.00
of which cohesion funds
€ 950,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 950000.00 |
Municipality | 825000.00 |
Payments monitored
€ 0.00
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Open
Expected start: 15/03/2023
Effective start: not available
Expected end: 15/06/2024
Effective end: not available
Entities
- Planning body
- REGIONE MOLISE, GIUNTA REGIONALE
- Implementing body
- COMUNE DI MACCHIA D'ISERNIA
- Beneficiary
- COMUNE DI MACCHIA D'ISERNIA
Programming area
- Programme
- PSC REGIONE MOLISE
- Fondo Aree Sottoutilizzate 2000-2006
- 2000-2006 Underutilized Areas Fund
- Cohesion funds
- € 950,000.00
- Payments on cohesion funds
- € 0.00
- Policy Area
- Istruzione e Formazione
- Sector of intervention
- Strutture educative e formative