CUP: B12C08000100002
EDIFICIO SCOLASTICO (COMPLETAMENTO DELL'EDIFICIO SEDE DI SCUOLA ELEMENTARE E MEDIA)
SUMMARY OF THE PROJECT
EDIFICIO SCOLASTICO (COMPLETAMENTO DELL'EDIFICIO SEDE DI SCUOLA ELEMENTARE E MEDIA)
Implementation indicator
Superficie oggetto di intervento
- Target
- 611 mq
- Achieved
- 460 mq
Funding monitored
€ 335,558.59
of which cohesion funds
€ 335,558.59
Given name | Amount |
---|---|
Development and Cohesion Fund | 335558.59 |
- Economies:
- € 58.22
Payments monitored
€ 335,558.59
of which cohesion funds
€ 335,558.59
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2012 | 90444.38 | 90444.38 | 26 |
2013 | 245114.21 | 335558.59 | 100 |
State of progress
Completed
Expected start: 29/06/2011
Effective start: 29/06/2011
Expected end: 10/10/2012
Effective end: 10/10/2012
Entities
- Planning body
- REGIONE MOLISE
- Implementing body
- COMUNE DI SPINETE
- Beneficiary
- REGIONE MOLISE
- Executor
- PISTILLI COSTRUZIONI SNC DI PISTILLI B. E C.
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE MOLISE
- Policy Area
- Istruzione e Formazione
- Sector of intervention
- Strutture educative e formative