CUP: F93J07000000002
MIRANDA: Sistema di accumulo e trasporto idrico a servizio dell'area pedemontana del Comune di Miranda
SUMMARY OF THE PROJECT
MIRANDA: Sistema di accumulo e trasporto idrico a servizio dell'area pedemontana del Comune di Miranda
Implementation indicator
Estensione della rete
- Target
- 0.30 km
- Achieved
- 0.30 km
Download project
Funding monitored
€ 344,465.06
of which cohesion funds
€ 344,465.06
Given name | Amount |
---|---|
Development and Cohesion Fund | 344465.06 |
Payments monitored
€ 344,465.06
of which cohesion funds
€ 344,465.06
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2007 | 250.00 | 250.00 | 0 |
2008 | 84749.21 | 84999.21 | 24 |
2009 | 217025.60 | 302024.81 | 87 |
2010 | 42440.25 | 344465.06 | 100 |
State of progress
Completed
Expected start: 28/02/2008
Effective start: 28/02/2008
Expected end: 23/03/2009
Effective end: 23/03/2009
Entities
- Planning body
- REGIONE MOLISE, GIUNTA REGIONALE
- Implementing body
- COMUNE DI MIRANDA
- Beneficiary
- REGIONE MOLISE, GIUNTA REGIONALE
Programming area
- Programme
- PSC REGIONE MOLISE
- Fondo Aree Sottoutilizzate 2000-2006
- 2000-2006 Underutilized Areas Fund
- Cohesion funds
- € 344,465.06
- Payments on cohesion funds
- € 344,465.06
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Risorse idriche