CUP: H89J06000010002
Completamento della rete idrica e fognante
SUMMARY OF THE PROJECT
Completamento della rete idrica e fognante
Implementation indicator
Estensione della rete
- Target
- 1.30 km
- Achieved
- 1.45 km
Download project
Funding monitored
€ 242,451.15
of which cohesion funds
€ 242,451.15
Given name | Amount |
---|---|
Development and Cohesion Fund | 242451.15 |
Payments monitored
€ 242,451.15
of which cohesion funds
€ 242,451.15
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2007 | 16454.79 | 16454.79 | 6 |
2008 | 162895.65 | 179350.44 | 73 |
2009 | 63100.71 | 242451.15 | 100 |
State of progress
Completed
Expected start: 28/09/2007
Effective start: 28/09/2007
Expected end: 20/02/2009
Effective end: 20/02/2009
Entities
- Planning body
- REGIONE MOLISE, GIUNTA REGIONALE
- Implementing body
- COMUNE DI BELMONTE DEL SANNIO
- Beneficiary
- REGIONE MOLISE, GIUNTA REGIONALE
Programming area
- Programme
- PSC REGIONE MOLISE
- Fondo Aree Sottoutilizzate 2000-2006
- 2000-2006 Underutilized Areas Fund
- Cohesion funds
- € 242,451.15
- Payments on cohesion funds
- € 242,451.15
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Risorse idriche
Other projects in territory
Same theme
Same type of investment
Realizzazione di un centro di aggregazione sociale con annesso ostello | € 422,136 |
Completamento funzionale e definitivo di riqualificazione di strade e piazze del centro urbano. | € 261,387 |