CUP: D75H05000080002
CASTEL SAN VINCENZO - Caduta massi centro abitato - Completamento
SUMMARY OF THE PROJECT
CASTEL SAN VINCENZO - Caduta massi centro abitato - Completamento
Implementation indicator
Non richesto (Migrazione PSC)
- Target
- 0.01 num
- Achieved
- 0.01 num
Download project
Funding monitored
€ 187,278.62
of which cohesion funds
€ 187,278.62
Given name | Amount |
---|---|
Development and Cohesion Fund | 187278.62 |
Payments monitored
€ 187,278.62
of which cohesion funds
€ 187,278.62
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2006 | 4970.00 | 4970.00 | 2 |
2007 | 113225.38 | 118195.38 | 63 |
2008 | 0 | 118195.38 | 63 |
2009 | 69083.24 | 187278.62 | 100 |
State of progress
Completed
Expected start: 05/07/2006
Effective start: 05/07/2006
Expected end: 14/07/2008
Effective end: 14/07/2008
Entities
- Planning body
- REGIONE MOLISE, GIUNTA REGIONALE
- Implementing body
- COMUNE DI CASTEL SAN VINCENZO
- Beneficiary
- REGIONE MOLISE, GIUNTA REGIONALE
Programming area
- Programme
- PSC REGIONE MOLISE
- Fondo Aree Sottoutilizzate 2000-2006
- 2000-2006 Underutilized Areas Fund
- Cohesion funds
- € 187,278.62
- Payments on cohesion funds
- € 187,278.62
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico