RESTAURO E CONSOLIDAMENTO CHIESA S. MARIA MAGGIORE - GUGLIONESI (CB) - ARCIDIOCESI DI TERMOLI-LARINO
SUMMARY OF THE PROJECT
RESTAURO E CONSOLIDAMENTO CHIESA S. MARIA MAGGIORE - GUGLIONESI (CB) - ARCIDIOCESI DI TERMOLI-LARINO
Implementation indicator
Superficie oggetto di intervento
- Target
- 500 mq
- Achieved
- 440 mq
Download project
Funding monitored
€ 672,106.63
of which cohesion funds
€ 384,060.93
Given name | Amount |
---|---|
Development and Cohesion Fund | 384060.93 |
Another public source | 288045.70 |
- Economies:
- € 27,893.37
Payments monitored
€ 672,106.63
of which cohesion funds
€ 384,060.93
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2013 | 79652.58 | 79652.58 | 11 |
2014 | 81596.62 | 161249.20 | 23 |
2015 | 194616.10 | 355865.30 | 52 |
2016 | 0 | 355865.30 | 52 |
2017 | 26432.36 | 382297.66 | 56 |
2018 | 1763.27 | 384060.93 | 57 |
2019 | 0 | 384060.93 | 57 |
2020 | 0 | 384060.93 | 57 |
2021 | 0 | 384060.93 | 57 |
2022 | 288045.70 | 672106.63 | 100 |
State of progress
Completed
Expected start: 06/09/2013
Effective start: 06/09/2013
Expected end: 18/10/2016
Effective end: 18/10/2016
Entities
- Planning body
- REGIONE MOLISE
- Implementing body
- DIOCESI DI TERMOLI-LARINO
- Beneficiary
- DIOCESI DI TERMOLI-LARINO
- Executor
- *INDIVIDUO*1MISEMOLBGB.52*
Programming area
- Programme
- PSC REGIONE MOLISE
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 384,060.93
- Payments on cohesion funds
- € 384,060.93
- Policy Area
- Cultura
- Sector of intervention
- Patrimonio e paesaggio
Other projects in territory
Same theme
Same type of investment
RIQUALIFICAZIONE AMBIENTALE SITO PAESAGGISTICO L. R. 24/89 SIC. | € 274,662 |