CUP: D35E05000110001
COMPLETAMENTO REALIZZAZIONE STRUTTURA MUSEALE A CASTEL SAN VINCENZO.
SUMMARY OF THE PROJECT
COMPLETAMENTO REALIZZAZIONE STRUTTURA MUSEALE A CASTEL SAN VINCENZO.
Implementation indicator
Superficie oggetto di intervento
- Target
- 1 mq
- Achieved
- 1 mq
Funding monitored
€ 399,159.57
of which cohesion funds
€ 399,159.57
Given name | Amount |
---|---|
Development and Cohesion Fund | 399159.57 |
Payments monitored
€ 399,159.57
of which cohesion funds
€ 399,159.57
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2005 | 108589.31 | 108589.31 | 27 |
2006 | 183773.70 | 292363.01 | 73 |
2007 | 70737.12 | 363100.13 | 90 |
2008 | 36059.44 | 399159.57 | 100 |
State of progress
Completed
Expected start: 09/12/2004
Effective start: 09/12/2004
Expected end: 23/06/2006
Effective end: 23/06/2006
Entities
- Planning body
- REGIONE MOLISE
- Implementing body
- COMUNE DI CASTEL SAN VINCENZO
- Beneficiary
- REGIONE MOLISE
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE MOLISE
- Policy Area
- Cultura
- Sector of intervention
- Patrimonio e paesaggio