CUP: H17H12002440001
Lavori di ripristino dei danni su strade comunali, Serra della Spina, Fontana Longa, Santa Maria, Crocella e centro abitato
SUMMARY OF THE PROJECT
Lavori di ripristino dei danni su strade comunali, Serra della Spina, Fontana Longa, Santa Maria, Crocella e centro abitato
Implementation indicator
Estensione in lunghezza
- Target
- 3.09 km
- Achieved
- 3.09 km
Download project
Funding monitored
€ 192,797.98
of which cohesion funds
€ 192,797.98
Given name | Amount |
---|---|
Development and Cohesion Fund | 192797.98 |
- Economies:
- € 7,202.02
Payments monitored
€ 192,797.98
of which cohesion funds
€ 192,797.98
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2016 | 128771.08 | 128771.08 | 66 |
2017 | 0 | 128771.08 | 66 |
2018 | 64026.90 | 192797.98 | 100 |
State of progress
Completed
Expected start: 08/04/2015
Effective start: 08/04/2015
Expected end: 11/07/2016
Effective end: 11/07/2016
Entities
- Planning body
- REGIONE MOLISE, GIUNTA REGIONALE
- Implementing body
- COMUNE DI MONACILIONI
- Beneficiary
- COMUNE DI MONACILIONI
- Executor
- R&P srl
Programming area
- Programme
- PSC REGIONE MOLISE
- 2007-2013 National Development and Cohesion Fund
- 2007-2013 National Development and Cohesion Fund
- Cohesion funds
- € 192,797.98
- Payments on cohesion funds
- € 192,797.98
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico