CUP: G91E14000210002
AZIONI, ATTIVIT ED INTERVENTI FINALIZZATI AL MIGLIORAMENTO DELL'EFFICIENZA DELLA RETE IDRICA COMUNALE
SUMMARY OF THE PROJECT
AZIONI, ATTIVIT ED INTERVENTI FINALIZZATI AL MIGLIORAMENTO DELL'EFFICIENZA DELLA RETE IDRICA COMUNALE
Implementation indicator
Estensione della rete
- Target
- 6.50 km
- Achieved
- 6.50 km
Download project
Funding monitored
€ 283,554.07
of which cohesion funds
€ 279,300.76
Given name | Amount |
---|---|
Development and Cohesion Fund | 279300.76 |
Municipality | 4253.31 |
- Economies:
- € 16,445.93
Payments monitored
€ 283,554.07
of which cohesion funds
€ 279,300.76
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2016 | 562.50 | 562.50 | 0 |
2017 | 210154.04 | 210716.54 | 74 |
2018 | 72837.53 | 283554.07 | 100 |
State of progress
Completed
Expected start: 05/04/2016
Effective start: 05/04/2016
Expected end: 21/04/2017
Effective end: 21/04/2017
Entities
- Planning body
- REGIONE MOLISE
- Implementing body
- COMUNE DI MORRONE DEL SANNIO
- Beneficiary
- COMUNE DI MORRONE DEL SANNIO
- Executor
- MAGISTRA S.R.L.
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE MOLISE
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Risorse idriche
Other projects in territory
Same theme
Same type of investment
REALIZZAZIONE DEL SISTEMA DI COLLETTAMENTO E DEPURATIVO A SERVIZIO DI UNA PARTE DEL CENTRO ABITATO | € 97,453 |