CUP: D74H14000370002
ATTIVIT , AZIONI ED INTERVENTI FINALIZZATI AL MIGLIORAMENTO DELL'EFFICIENZA DELLA RETE IDRICA COMUNALE
SUMMARY OF THE PROJECT
ATTIVIT , AZIONI ED INTERVENTI FINALIZZATI AL MIGLIORAMENTO DELL'EFFICIENZA DELLA RETE IDRICA COMUNALE
Download project
Funding monitored
€ 234,122.97
of which cohesion funds
€ 230,611.13
Given name | Amount |
---|---|
Development and Cohesion Fund | 230611.13 |
Municipality | 3511.84 |
- Economies:
- € 65,877.03
Payments monitored
€ 187,376.08
of which cohesion funds
€ 184,565.44
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 148962.00 | 148962.00 | 63 |
2020 | 0 | 148962.00 | 63 |
2021 | 0 | 148962.00 | 63 |
2022 | 0 | 148962.00 | 63 |
2023 | 0 | 148962.00 | 63 |
2024 | 38414.08 | 187376.08 | 80 |
State of progress
Open
Expected start: 21/09/2016
Effective start: 21/09/2016
Expected end: 10/07/2020
Effective end: 10/07/2020
Entities
- Planning body
- REGIONE MOLISE
- Implementing body
- COMUNE DI CIVITACAMPOMARANO
- Beneficiary
- COMUNE DI CIVITACAMPOMARANO
- Executor
- EDIL VALLE
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE MOLISE
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Risorse idriche