CUP: H53J13001470003
SISTEMAZIONE DEI DISSESTI IDROGEOLOGICI NEL TERRITORIO COMUNALE. STRADA COMUNALE'COSTE-LIRA-MALDI'. - COMUNE DI CANTALUPO NEL SANNIO - IS
SUMMARY OF THE PROJECT
SISTEMAZIONE DEI DISSESTI IDROGEOLOGICI NEL TERRITORIO COMUNALE. STRADA COMUNALE'COSTE-LIRA-MALDI'. - COMUNE DI CANTALUPO NEL SANNIO - IS
Implementation indicator
Superficie oggetto di intervento (Ha)
- Target
- 1,300 ha
- Achieved
- 1,300 ha
Download project
Funding monitored
€ 193,757.38
of which cohesion funds
€ 193,757.38
Given name | Amount |
---|---|
Development and Cohesion Fund | 193757.38 |
- Economies:
- € 6,242.62
Payments monitored
€ 193,757.38
of which cohesion funds
€ 193,757.38
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2014 | 38445.37 | 38445.37 | 19 |
2015 | 0 | 38445.37 | 19 |
2016 | 35000.00 | 73445.37 | 37 |
2017 | 114312.01 | 187757.38 | 96 |
2018 | 0 | 187757.38 | 96 |
2019 | 6000.00 | 193757.38 | 100 |
State of progress
Completed
Expected start: 23/09/2015
Effective start: 23/09/2015
Expected end: 16/02/2016
Effective end: 16/02/2016
Entities
- Planning body
- REGIONE MOLISE
- Implementing body
- COMUNE DI CANTALUPO NEL SANNIO
- Beneficiary
- COMUNE DI CANTALUPO NEL SANNIO
- Executor
- MASUCCI
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE MOLISE
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico