Terminal autobus - completamento percorso pedonale
SUMMARY OF THE PROJECT
Terminal autobus - completamento percorso pedonale
Implementation indicator
Superficie oggetto di intervento
- Target
- 750 mq
- Achieved
- 750 mq
Download project
Funding monitored
€ 1,696,765.86
of which cohesion funds
€ 1,696,765.86
Given name | Amount |
---|---|
Development and Cohesion Fund | 1696765.86 |
- Economies:
- € 103,234.14
Payments monitored
€ 1,696,765.86
of which cohesion funds
€ 1,696,765.86
100%
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2016 | 1098.08 | 1098.08 | 0 |
2017 | 1165.65 | 2263.73 | 0 |
2018 | 14890.47 | 17154.20 | 1 |
2019 | 402878.21 | 420032.41 | 24 |
2020 | 3164.82 | 423197.23 | 24 |
2021 | 651924.78 | 1075122.01 | 63 |
2022 | 618332.73 | 1693454.74 | 99 |
2023 | 3311.12 | 1696765.86 | 100 |
State of progress
Completed
Expected start: 01/02/2019
Effective start: 04/02/2019
Expected end: 25/09/2022
Effective end: 25/05/2022
Entities
- Planning body
- REGIONE MOLISE, GIUNTA REGIONALE
- Implementing body
- COMUNE DI CAMPOBASSO
- Beneficiary
- COMUNE DI CAMPOBASSO
- Executor
- PQ Edilizia e strade
Programming area
- Programme
- PSC REGIONE MOLISE
- 2007-2013 National Development and Cohesion Fund
- 2007-2013 National Development and Cohesion Fund
- Cohesion funds
- € 1,696,765.86
- Payments on cohesion funds
- € 1,696,765.86
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Mobilita' urbana