CUP: J14H15000600002
Metropolitana leggera - I lotto Matrice-Bojano
SUMMARY OF THE PROJECT
Metropolitana leggera - I lotto Matrice-Bojano
Implementation indicator
Estensione in lunghezza
- Target
- 41.10 km
- Achieved
- 37.92 km
Download project
Funding monitored
€ 23,500,000.00
of which cohesion funds
€ 23,500,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 23500000.00 |
Payments monitored
€ 21,513,006.07
of which cohesion funds
€ 21,513,006.07
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2016 | 198045.35 | 198045.35 | 0 |
2017 | 4643703.11 | 4841748.46 | 20 |
2018 | 9238877.35 | 14080625.81 | 59 |
2019 | 5247523.68 | 19328149.49 | 82 |
2020 | 1882646.77 | 21210796.26 | 90 |
2021 | 302209.81 | 21513006.07 | 91 |
State of progress
Open
Expected start: 03/11/2016
Effective start: 03/11/2016
Expected end: 31/03/2021
Effective end: 30/07/2020
Entities
- Planning body
- REGIONE MOLISE, GIUNTA REGIONALE
- Implementing body
- RFI
- Beneficiary
- RFI
- Executor
-
R.T.I. Ferone Pietro & C. srl (Capogruppo Mandataria) e Anzano srl Costruzione e Impianti (Mandante)
MER MEC Spa
Programming area
- Programme
- PSC REGIONE MOLISE
- 2007-2013 National Development and Cohesion Fund
- 2007-2013 National Development and Cohesion Fund
- Cohesion funds
- € 23,500,000.00
- Payments on cohesion funds
- € 21,513,006.07
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto ferroviario
At the School of OpenCohesion
OpenCoesione goes to School followed this project in edition 2018-19 with the team “FastUrbanRail” of “LICEO SCIENTIFICO M. PAGANO” of Campobasso, CAMPOBASSO.
Read the Monithon report.
View the creative output.
Read the Monithon report.