CUP: E72F07000110001
PORTO DI CIVITANOVA MARCHE - Realizzazione di pontile a giorno per pescherecci sul molo EST
SUMMARY OF THE PROJECT
PORTO DI CIVITANOVA MARCHE - Realizzazione di pontile a giorno per pescherecci sul molo EST
Implementation indicator
Superficie oggetto di intervento
- Target
- 1,410 mq
- Achieved
- 1,410 mq
Download project
Funding monitored
€ 1,845,288.06
of which cohesion funds
€ 1,845,288.06
Given name | Amount |
---|---|
Development and Cohesion Fund | 1845288.06 |
Payments monitored
€ 1,845,288.06
of which cohesion funds
€ 1,845,288.06
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2007 | 21253.53 | 21253.53 | 1 |
2008 | 1520479.82 | 1541733.35 | 83 |
2009 | 28527.02 | 1570260.37 | 85 |
2010 | 3276.00 | 1573536.37 | 85 |
2011 | 0 | 1573536.37 | 85 |
2012 | 0 | 1573536.37 | 85 |
2013 | 0 | 1573536.37 | 85 |
2014 | 0 | 1573536.37 | 85 |
2015 | 0 | 1573536.37 | 85 |
2016 | 271751.69 | 1845288.06 | 100 |
State of progress
Completed
Expected start: 29/10/2007
Effective start: 29/10/2007
Expected end: 14/06/2008
Effective end: 14/06/2008
Entities
- Planning body
- COMUNE DI CIVITANOVA MARCHE
- Implementing body
- COMUNE DI CIVITANOVA MARCHE
- Beneficiary
- REGIONE MARCHE
Programming area
- Programme
- PSC REGIONE MARCHE
- Fondo Aree Sottoutilizzate 2000-2006
- 2000-2006 Underutilized Areas Fund
- Cohesion funds
- € 1,845,288.06
- Payments on cohesion funds
- € 1,845,288.06
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto marittimo