CUP: B15F03000000011
POTENZIAMENTO E CAPTAZIONE RETE IDRICA - PROGETTO 2: INTERVENTI DI SISTEMAZIONE DELL'AREA DI PERTINENZA DEI POZZI IN LOCALITA' GERE
SUMMARY OF THE PROJECT
POTENZIAMENTO E CAPTAZIONE RETE IDRICA - PROGETTO 2: INTERVENTI DI SISTEMAZIONE DELL'AREA DI PERTINENZA DEI POZZI IN LOCALITA' GERE
Implementation indicator
Non richesto (Migrazione PSC)
- Target
- 0.01 num
- Achieved
- 0.01 num
Download project
Funding monitored
€ 97,634.18
of which cohesion funds
€ 40,178.67
Given name | Amount |
---|---|
Development and Cohesion Fund | 40178.67 |
Municipality | 57455.51 |
Payments monitored
€ 97,634.18
of which cohesion funds
€ 40,178.67
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2004 | 59613.79 | 59613.79 | 61 |
2005 | 38020.39 | 97634.18 | 100 |
State of progress
Completed
Expected start: 05/04/2004
Effective start: 05/04/2004
Expected end: 05/11/2004
Effective end: 05/11/2004
Entities
- Planning body
- COMUNE DI GARDONE RIVIERA
- Implementing body
- COMUNE DI GARDONE RIVIERA
- Beneficiary
- REGIONE LOMBARDIA
Programming area
- Programme
- PSC REGIONE LOMBARDIA
- Fondo Aree Sottoutilizzate 2000-2006
- 2000-2006 Underutilized Areas Fund
- Cohesion funds
- € 40,178.67
- Payments on cohesion funds
- € 40,178.67
- Policy Area
- Competitivita' Imprese
- Sector of intervention
- Industria e servizi