CUP: H41B07000000007
Ripristino e riqualificazione del sentiero ciclopedonale e dell'area attorno alla chiesetta di Santa Maria in Binda
SUMMARY OF THE PROJECT
Ripristino e riqualificazione del sentiero ciclopedonale e dell'area attorno alla chiesetta di Santa Maria in Binda
Implementation indicator
Estensione in lunghezza
- Target
- 0.37 km
- Achieved
- 0.37 km
Download project
Funding monitored
€ 238,983.59
of which cohesion funds
€ 215,085.23
Given name | Amount |
---|---|
Development and Cohesion Fund | 215085.23 |
Municipality | 23898.36 |
Payments monitored
€ 238,983.58
of which cohesion funds
€ 215,085.22
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2005 | 11305.81 | 11305.81 | 4 |
2006 | 15092.74 | 26398.55 | 11 |
2007 | 6441.61 | 32840.16 | 13 |
2008 | 92908.98 | 125749.14 | 52 |
2009 | 113234.44 | 238983.58 | 99 |
State of progress
Completed
Expected start: 01/02/2008
Effective start: 01/02/2008
Expected end: 19/07/2008
Effective end: 19/07/2008
Entities
- Planning body
- COMUNE DI NOSATE
- Implementing body
- COMUNE DI NOSATE
- Beneficiary
- REGIONE LOMBARDIA
Programming area
- Programme
- PSC REGIONE LOMBARDIA
- Fondo Aree Sottoutilizzate 2000-2006
- 2000-2006 Underutilized Areas Fund
- Cohesion funds
- € 215,085.23
- Payments on cohesion funds
- € 215,085.22
- Policy Area
- Riqualificazione urbana
- Sector of intervention