CUP: J37H07000580002
Ex S.S. 453 'Della Valle D' Arroscia'. Adeguamento e messa in sicurezza sede stradale ed opere d'arte tra le progressive km 17+300 e 18+200 in Comune di Ortovero
SUMMARY OF THE PROJECT
Ex S.S. 453 'Della Valle D' Arroscia'. Adeguamento e messa in sicurezza sede stradale ed opere d'arte tra le progressive km 17+300 e 18+200 in Comune di Ortovero
Implementation indicator
Estensione dell'intervento in lunghezza
- Target
- 900 m
- Achieved
- 900 m
Download project
Funding monitored
€ 1,094,891.72
of which cohesion funds
€ 1,094,891.72
Given name | Amount |
---|---|
Development and Cohesion Fund | 1094891.72 |
- Economies:
- € 5,108.28
Payments monitored
€ 1,094,891.72
of which cohesion funds
€ 1,094,891.72
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2007 | 6240.00 | 6240.00 | 0 |
2008 | 47731.08 | 53971.08 | 4 |
2009 | 400601.94 | 454573.02 | 41 |
2010 | 636161.18 | 1090734.20 | 99 |
2011 | 4157.52 | 1094891.72 | 100 |
State of progress
Completed
Expected start: 03/03/2009
Effective start: 03/03/2009
Expected end: 12/08/2010
Effective end: 12/08/2010
Entities
- Planning body
- AMMINISTRAZIONE PROVINCIALE DI SAVONA
- Implementing body
- AMMINISTRAZIONE PROVINCIALE DI SAVONA
- Beneficiary
- ISTITUTO NAZIONALE DELLA PREVIDENZA SOCIALE - INPS
Programming area
- Programme
- PSC REGIONE LIGURIA
- Fondo Aree Sottoutilizzate 2000-2006
- 2000-2006 Underutilized Areas Fund
- Cohesion funds
- € 1,094,891.72
- Payments on cohesion funds
- € 1,094,891.72
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Mobilita' urbana