COMPLETAMENTO DELLA STRADA DI ALLACCIAMENTO FRAZIONE COLLINARE FOLLO ALTO - SORBOLO - LOC. MADONNA DEL CARMINE
SUMMARY OF THE PROJECT
COMPLETAMENTO DELLA STRADA DI ALLACCIAMENTO FRAZIONE COLLINARE FOLLO ALTO - SORBOLO - LOC. MADONNA DEL CARMINE
Implementation indicator
Estensione dell'intervento in lunghezza
- Target
- 2,000 m
- Achieved
- 2,000 m
Funding monitored
€ 307,078.81
of which cohesion funds
€ 241,188.49
Given name | Amount |
---|---|
Development and Cohesion Fund | 241188.49 |
Municipality | 65890.32 |
Payments monitored
€ 307,078.81
of which cohesion funds
€ 241,188.49
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2004 | 12980.00 | 12980.00 | 4 |
2005 | 105905.61 | 118885.61 | 38 |
2006 | 173935.05 | 292820.66 | 95 |
2007 | 3600.00 | 296420.66 | 96 |
2008 | 10658.15 | 307078.81 | 100 |
State of progress
Completed
Expected start: 09/12/2004
Effective start: 09/12/2004
Expected end: 24/02/2006
Effective end: 24/02/2006
Entities
- Planning body
- REGIONE LIGURIA
- Implementing body
- COMUNE DI FOLLO
- Beneficiary
- REGIONE LIGURIA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE LIGURIA
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Mobilita' urbana