CUP: B35C16000030001
RECUPERO E RIQUALIFICAZIONE DEL COMPLESSO DELLA CITTADELLA DI ANCONA - RECUPERO E RESTAURO DELLA CINTA MURARIA E PULIZIA CORTILE E AREE INTERNE ALLE MURA
SUMMARY OF THE PROJECT
RECUPERO E RIQUALIFICAZIONE DEL COMPLESSO DELLA CITTADELLA DI ANCONA - RECUPERO E RESTAURO DELLA CINTA MURARIA E PULIZIA CORTILE E AREE INTERNE ALLE MURA
Implementation indicator
Superficie oggetto di intervento
- Target
- 1,000 mq
- Achieved
- 600 mq
Download project
Funding monitored
€ 3,000,000.00
of which cohesion funds
€ 3,000,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 3000000.00 |
Payments monitored
€ 2,014,906.91
of which cohesion funds
€ 2,014,906.91
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2021 | 24054.37 | 24054.37 | 0 |
2022 | 42843.89 | 66898.26 | 2 |
2023 | 653365.21 | 720263.47 | 24 |
2024 | 456058.03 | 1176321.50 | 39 |
2025 | 838585.41 | 2014906.91 | 67 |
State of progress
Open
Expected start: 01/01/2019
Effective start: 19/12/2022
Expected end: 31/12/2019
Effective end: not available
Entities
- Planning body
- MINISTERO DEI BENI E DELLE ATTIVITA' CULTURALI E DEL TURISMO
- Implementing body
- REGIONE MARCHE
- Beneficiary
- REGIONE MARCHE
Programming area
- Programme
- PSC MINISTERO CULTURA
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 3,000,000.00
- Payments on cohesion funds
- € 2,014,906.91
- Policy Area
- Cultura
- Sector of intervention
- Patrimonio e paesaggio