CUP: E55C15000090001
WATERFRONT MAR PICCOLO - RIQUALIFICAZIONE E RINATURALIZZAZIONE DEL WATERFRONT MAR PICCOLO CHE PARTE DA VIA NUOVA, OLTRE IL PONTE DI PIETRA, SINO AL PIAZZALE DEMOCRATE
SUMMARY OF THE PROJECT
WATERFRONT MAR PICCOLO - RIQUALIFICAZIONE E RINATURALIZZAZIONE DEL WATERFRONT MAR PICCOLO CHE PARTE DA VIA NUOVA, OLTRE IL PONTE DI PIETRA, SINO AL PIAZZALE DEMOCRATE
Implementation indicator
Superficie oggetto di intervento
- Target
- 19,400 mq
- Achieved
- 1 mq
Funding monitored
€ 6,000,000.00
of which cohesion funds
€ 6,000,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 6000000.00 |
Payments monitored
€ 124,065.22
of which cohesion funds
€ 124,065.22
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2023 | 124065.22 | 124065.22 | 2 |
State of progress
Open
Expected start: 01/03/2025
Effective start: not available
Expected end: 30/08/2026
Effective end: not available
Entities
- Planning body
- MINISTERO DEI BENI E DELLE ATTIVITA' CULTURALI E DEL TURISMO
- Implementing body
- COMUNE DI TARANTO
- Beneficiary
- COMUNE DI TARANTO
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC MINISTERO CULTURA
- Policy Area
- Cultura
- Sector of intervention
- Patrimonio e paesaggio