CUP: I15F20000010009
CORSO UMBERTO I*CORSO UMBERTO I*LAVORI DI RIQUALIFICAZIONE
SUMMARY OF THE PROJECT
CORSO UMBERTO I*CORSO UMBERTO I*LAVORI DI RIQUALIFICAZIONE
Implementation indicators
Popolazione beneficiaria di servizi /infrastrutture migliori (eccetto ICT)
- Target
- 100 num
- Achieved
- 5,480 num
Beni o risorse o patrimonio culturali valorizzati
- Target
- 1 num
- Achieved
- 1 num
Programmi di sviluppo turistico sostenuti
- Target
- 100 num
- Achieved
- 100 num
- Slide 1
- Slide 2
- Slide 3
Download project
Funding monitored
€ 904,000.00
of which cohesion funds
€ 904,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 904000.00 |
Payments monitored
€ 631,372.14
of which cohesion funds
€ 631,372.14
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2023 | 344982.24 | 344982.24 | 38 |
2024 | 286389.90 | 631372.14 | 69 |
State of progress
Open
Expected start: 28/12/2022
Effective start: 11/04/2023
Expected end: 26/06/2024
Effective end: 14/06/2024
Entities
- Planning body
- Ministero per i Beni e le Attivita Culturali -SG
- Implementing body
- COMUNE DI SAMBUCA DI SICILIA
- Beneficiary
- COMUNE DI SAMBUCA DI SICILIA
Programming area
- Programme
- PSC MINISTERO CULTURA
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 904,000.00
- Payments on cohesion funds
- € 631,372.14
- Policy Area
- Competitivita' Imprese
- Sector of intervention
- Turismo e ospitalita'