This project is eliminated from views and totals because it was never started in the Operational Programme of the 2007-2013 period.
Updated on 31/12/2020
Funding monitored € 27,819,893.45 of which cohesion funds € 27,819,893.45
Given name Amount
European Union20864920.08
Revolving Fund (National co-financing)6954973.37
Payments monitored € 27,819,893.45 of which cohesion funds € 27,819,893.45
Year Amount Cumulative amount Percentage on public financing
20104000000.004000000.0014
201141000000.0045000000.00161
2012045000000.00161
201322000000.0067000000.00240
2014067000000.00240
2015067000000.00240
2016067000000.00240
2017-39180106.5527819893.45100

State of progress

Completed
Expected start: 28/12/2010
Effective start: 28/12/2010
Expected end: 30/06/2015
Effective end: 08/03/2017

Type

Theme

Territory

Entities

Planning body
MIMIT MINISTERO DELLE IMPRESE E DEL MADE IN ITALY
Implementing body
MIMIT MINISTERO DELLE IMPRESE E DEL MADE IN ITALY
Beneficiary
MIMIT MINISTERO DELLE IMPRESE E DEL MADE IN ITALY
Priority QSN
Energia e ambiente: uso sostenibile e efficiente delle risorse per lo sviluppo
General objective QSN
Promuovere le opportunità di sviluppo locale attraverso l'attivazione di filiere produttive collegate all'aumento della quota di energia prodotta da fonti rinnovabili e al risparmio energetico
Specific objective QSN
Promozione dell'efficienza energetica e del risparmio dell'energia

Programming area

European Regional Development Fund (ERDF)
2007-2013 EU Structural Funds
Programme
IROP CONV ERDF RENEWABLE ENERGY AND ENERGY CONSERVATION
Axis
Asse II Efficienza energetica ed ottimizzazione del sistema
Operational objective
Identificare e realizzare modelli di intervento integrati o di filiera per l'efficienza energetica per l'efficienza energetica.