VICO DEL GARGANO - LAVORI DI SISTEMAZIONE E LA REGIMENTAZIONE DEL TORRENTE VALLE DEL MELAINO
SUMMARY OF THE PROJECT
VICO DEL GARGANO - LAVORI DI SISTEMAZIONE E LA REGIMENTAZIONE DEL TORRENTE VALLE DEL MELAINO
Download project
Funding monitored
€ 4,220,000.00
of which cohesion funds
€ 4,220,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 4220000.00 |
Payments monitored
€ 3,902,819.40
of which cohesion funds
€ 3,902,819.40
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2015 | 142005.91 | 142005.91 | 3 |
2016 | 118336.43 | 260342.34 | 6 |
2017 | 84310.14 | 344652.48 | 8 |
2018 | 980478.01 | 1325130.49 | 31 |
2019 | 1503523.53 | 2828654.02 | 67 |
2020 | 938239.16 | 3766893.18 | 89 |
2021 | 14991.90 | 3781885.08 | 89 |
2022 | 120934.32 | 3902819.40 | 92 |
State of progress
Open
Expected start: 03/07/2017
Effective start: 03/07/2017
Expected end: 28/11/2019
Effective end: 28/11/2019
Entities
- Planning body
- REGIONE PUGLIA
- Implementing body
- COMMISSARIO STRAORDINARIO PER L'ATTUAZIONE DEGLI INTERVENTI PER LA MITIGAZIONE DEL RISCHIO IDROGEOLOGICO NELLA REGIONE PUGLIA
- Beneficiary
- COMUNE DI VICO DEL GARGANO
Programming area
- Programme
- PSC REGIONE PUGLIA
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 4,220,000.00
- Payments on cohesion funds
- € 3,902,819.40
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Risorse idriche