CUP: J15D12000090003
CELENZA VALFORTORE - Completamento lavori di consolidamento e messa in sicurezza del versante collinare - Centro urbano- valle Via Regina Margherita
SUMMARY OF THE PROJECT
CELENZA VALFORTORE - Completamento lavori di consolidamento e messa in sicurezza del versante collinare - Centro urbano- valle Via Regina Margherita
Implementation indicator
Non richesto (Migrazione PSC)
- Target
- 0.01 num
- Achieved
- 0.01 num
Download project
Funding monitored
€ 2,270,000.00
of which cohesion funds
€ 2,270,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 2270000.00 |
Payments monitored
€ 1,694,879.62
of which cohesion funds
€ 1,694,879.62
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2013 | 21637.10 | 21637.10 | 0 |
2014 | 102661.80 | 124298.90 | 5 |
2015 | 633300.60 | 757599.50 | 33 |
2016 | 479066.12 | 1236665.62 | 54 |
2017 | 314418.25 | 1551083.87 | 68 |
2018 | 134163.26 | 1685247.13 | 74 |
2019 | 9632.49 | 1694879.62 | 74 |
State of progress
Open
Expected start: 03/06/2014
Effective start: 02/07/2015
Expected end: 06/12/2015
Effective end: 10/04/2017
Entities
- Planning body
- REGIONE PUGLIA
- Implementing body
- COMMISSARIO STRAORDINARIO PER L'ATTUAZIONE DEGLI INTERVENTI PER LA MITIGAZIONE DEL RISCHIO IDROGEOLOGICO NELLA REGIONE PUGLIA
- Beneficiary
- COMUNE DI CELENZA VALFORTORE
Programming area
- Programme
- PSC REGIONE PUGLIA
- 2007-2013 National Development and Cohesion Fund
- 2007-2013 National Development and Cohesion Fund
- Cohesion funds
- € 2,270,000.00
- Payments on cohesion funds
- € 1,694,879.62
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Risorse idriche