CUP: F11B21008260001
Messa in sicurezza del territorio con la funzionalizzazione del sistema di drenaggio urbano
SUMMARY OF THE PROJECT
MESSA IN SICUREZZA DEL TERRITORIO CON LA FUNZIONALIZZAZIONE DEL SISTEMA DI DRENAGGIO URBANO.*CORSO I OTTOBRE*MESSA IN SICUREZZA DEL TERRITORIO CON LA FUNZIONALIZZAZIONE DEL SISTEMA DI DRENAGGIO URBANO.
Implementation indicator
Estensione della rete
- Target
- 3 km
- Achieved
- 0.70 km
Download project
Funding monitored
€ 2,078,322.21
of which cohesion funds
€ 2,078,322.21
Given name | Amount |
---|---|
Development and Cohesion Fund | 2078322.21 |
Payments monitored
€ 633,990.35
of which cohesion funds
€ 633,990.35
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2024 | 362581.68 | 362581.68 | 17 |
2025 | 271408.67 | 633990.35 | 30 |
State of progress
Open
Expected start: 04/09/2024
Effective start: 12/09/2024
Expected end: 30/06/2025
Effective end: not available
Entities
- Planning body
- COMUNE DI MADDALONI
- Implementing body
- COMUNE DI MADDALONI
- Beneficiary
- COMUNE DI MADDALONI
- Executor
- COMUNE DI MADDALONI
Programming area
- Programme
- CIS TERRA DEI FUOCHI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 2,078,322.21
- Payments on cohesion funds
- € 633,990.35
- Policy Area
- Ambiente e Risorse Naturali
- Sector of intervention
- Rischi e Adattamento Climatico