CUP: G24B13000210002
IDROVORA DI MONDINE - NUOVO IMPIANTO IRRIGUO
SUMMARY OF THE PROJECT
IDROVORA DI MONDINE - NUOVO IMPIANTO IRRIGUO
Implementation indicator
Superficie oggetto di intervento
- Target
- 60,000 mq
- Achieved
- 60,000 mq
Download project
Funding monitored
€ 2,506,020.27
of which cohesion funds
€ 2,506,020.27
Given name | Amount |
---|---|
Development and Cohesion Fund | 2506020.27 |
- Economies:
- € 493,979.73
Payments monitored
€ 2,506,020.27
of which cohesion funds
€ 2,506,020.27
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2014 | 56318.62 | 56318.62 | 2 |
2015 | 4521.00 | 60839.62 | 2 |
2016 | 15058.44 | 75898.06 | 3 |
2017 | 1701884.30 | 1777782.36 | 70 |
2018 | 111481.27 | 1889263.63 | 75 |
2019 | 616756.64 | 2506020.27 | 100 |
State of progress
Completed
Expected start: 18/01/2016
Effective start: 18/01/2016
Expected end: 29/01/2018
Effective end: 29/01/2018
Entities
- Planning body
- REGIONE EMILIA-ROMAGNA
- Implementing body
- CONSORZIO DI BONIFICA DELL'EMILIA CENTRALE
- Beneficiary
- CONSORZIO DI BONIFICA DELL'EMILIA CENTRALE
- Executor
- ELETTROMECCANICA MANFREDINI
Programming area
- Programme
- PSC EMILIA-ROMAGNA
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 2,506,020.27
- Payments on cohesion funds
- € 2,506,020.27
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Risorse idriche
Other projects in territory
Same theme
NODO IDRAULICO DI MONDINE: COMPLETAMENTO IMPIANTO IDROVORO | € 5,876,534 |
CHIAVICA EMISSARIA DI MONDINE: NUOVA CHIAVICA | € 2,454,651 |
MAGAZZINO DI MONDINE: RIPRISTINO E MIGLIORAMENTO SISMICO | € 189,758 |