Updated on 31/12/2024
Funding monitored € 3,834,771.92 of which cohesion funds € 6,228,104.00
Given name Amount
Development and Cohesion Fund3114052.00
Municipality720719.92
Economies:
€ 1,894.66
Payments monitored € 3,834,771.92 of which cohesion funds € 6,228,103.98
Year Amount Cumulative amount Percentage on public financing
2014944177.14944177.1424
20156614622.627558799.76197
2016110349.147669148.90199
2017394.947669543.84200

State of progress

Completed
Expected start: 27/04/2015
Effective start: 27/04/2015
Expected end: 13/08/2015
Effective end: 13/08/2015

Type

Theme

Territory

Entities

Planning body
REGIONE EMILIA-ROMAGNA
Implementing body
COMUNE DI CENTO
Beneficiary
COMUNE DI CENTO
Executor
Sistem Costruzioni
Priority QSN
Energia e ambiente: uso sostenibile e efficiente delle risorse per lo sviluppo
General objective QSN
Garantire le condizioni di sostenibilità ambientale dello sviluppo e livelli adeguati di servizi ambientali per la popolazione e le imprese
Specific objective QSN
Accrescere la capacità di offerta, la qualità e l'efficienza del servizio idrico, e rafforzare la difesa del suolo e la prevenzione dei rischi naturali

Programming area

Programme
PROGRAMMA ATTUATIVO SPECIALE FSC RICOSTRUZIONE PER SISMA 2012 EMILIA ROMAGNA
2007-2013 National Development and Cohesion Fund
2007-2013 National Development and Cohesion Fund
Cohesion funds
€ 3,114,052.00
Payments on cohesion funds
€ 3,114,052.00
Line
11 - Interventi per scuole danneggiate da eventi sismici 2012
Action
Interventi di ripristino funzionalità scuole
Programme
PSC EMILIA-ROMAGNA
2007-2013 National Development and Cohesion Fund
2007-2013 National Development and Cohesion Fund
Cohesion funds
€ 3,114,052.00
Payments on cohesion funds
€ 3,114,051.98
Policy Area
Ambiente e risorse naturali
Sector of intervention
Risorse idriche

Other projects in territory