CUP: J71B07000140001
RIQUALIFICAZIONE DEL SISTEMA DI VIABILITA' RURALE - AREA OB. 2 'BASSO FERRARESE' VARIANTE SP 29 - COSTRUZIONE CIRCONVALLAZIONE
SUMMARY OF THE PROJECT
RIQUALIFICAZIONE DEL SISTEMA DI VIABILITA' RURALE - AREA OB. 2 'BASSO FERRARESE' VARIANTE SP 29 - COSTRUZIONE CIRCONVALLAZIONE
Implementation indicator
Estensione in lunghezza
- Target
- 0.83 km
- Achieved
- 0.83 km
Download project
Funding monitored
€ 858,508.85
of which cohesion funds
€ 834,691.32
Given name | Amount |
---|---|
Development and Cohesion Fund | 834691.32 |
Municipality | 23817.53 |
- Economies:
- € 127,451.15
Payments monitored
€ 858,508.85
of which cohesion funds
€ 834,691.31
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2009 | 375622.05 | 375622.05 | 43 |
2010 | 466544.34 | 842166.39 | 98 |
2011 | 0 | 842166.39 | 98 |
2012 | 4981.95 | 847148.34 | 98 |
2013 | 11360.51 | 858508.85 | 100 |
State of progress
Completed
Expected start: 23/04/2009
Effective start: 23/04/2009
Expected end: 15/06/2010
Effective end: 15/06/2010
Entities
- Planning body
- REGIONE EMILIA-ROMAGNA
- Implementing body
- COMUNE DI MIGLIARO
- Beneficiary
- REGIONE EMILIA-ROMAGNA
Programming area
- Programme
- PSC EMILIA-ROMAGNA
- Fondo Aree Sottoutilizzate 2000-2006
- 2000-2006 Underutilized Areas Fund
- Cohesion funds
- € 834,691.32
- Payments on cohesion funds
- € 834,691.31
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale