CUP: G97B15000480001
PROGETTO PER LA BONIFICA IDRAULICA DELLA PIANA DI GALDO
SUMMARY OF THE PROJECT
PROGETTO PER LA BONIFICA IDRAULICA DELLA PIANA DI GALDO
Implementation indicator
Superficie oggetto di intervento
- Target
- 1,200,000 mq
- Achieved
- 1,200,000 mq
Download project
Funding monitored
€ 9,850,000.00
of which cohesion funds
€ 9,850,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 9850000.00 |
Payments monitored
€ 8,304,542.64
of which cohesion funds
€ 8,304,542.64
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2016 | 800.00 | 800.00 | 0 |
2017 | 8357.00 | 9157.00 | 0 |
2018 | 66193.41 | 75350.41 | 0 |
2019 | 62944.89 | 138295.30 | 1 |
2020 | 9576.25 | 147871.55 | 1 |
2021 | 2760879.37 | 2908750.92 | 29 |
2022 | 2831186.12 | 5739937.04 | 58 |
2023 | 2514212.92 | 8254149.96 | 83 |
2024 | 50392.68 | 8304542.64 | 84 |
State of progress
Open
Expected start: 31/03/2021
Effective start: 31/03/2021
Expected end: 08/09/2023
Effective end: 08/09/2023
Entities
- Planning body
- COMUNE DI LAURIA
- Implementing body
- COMUNE DI LAURIA
- Beneficiary
- COMUNE DI LAURIA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE BASILICATA
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico