CUP: I23D15000460007
IMPIANTO FOTOVOLTAICO CONNESSO IN RETE - IMPIANTO A POMPA DI CALORE PER LA CLIMATIZZAZIONE A SERVIZIO DEL CENTRO POLIVALENTE
Download project
Funding monitored
€ 135,810.00
of which cohesion funds
€ 135,810.00
Given name | Amount |
---|---|
European Union | 101857.50 |
Revolving Fund (National co-financing) | 33952.50 |
Payments monitored
€ 135,810.00
of which cohesion funds
€ 135,810.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2015 | 135810.00 | 135810.00 | 100 |
State of progress
Completed
Expected start: 12/09/2015
Effective start: 21/10/2015
Expected end: 13/10/2015
Effective end: 11/11/2015
Type
- Infrastructure
- ALTRO
Theme
- Energy
- Efficienza dell'energia, cogenerazione, gestione dell'energia
Territory
Entities
- Planning body
- MIMIT MINISTERO DELLE IMPRESE E DEL MADE IN ITALY
- Implementing body
- COMUNE DI CRUCOLI
- Beneficiary
- COMUNE DI CRUCOLI
- Priority QSN
- Energia e ambiente: uso sostenibile e efficiente delle risorse per lo sviluppo
- General objective QSN
- Promuovere le opportunità di sviluppo locale attraverso l'attivazione di filiere produttive collegate all'aumento della quota di energia prodotta da fonti rinnovabili e al risparmio energetico
- Specific objective QSN
- Promozione dell'efficienza energetica e del risparmio dell'energia
Programming area
- European Regional Development Fund (ERDF)
- 2007-2013 EU Structural Funds
- Programme
- IROP CONV ERDF RENEWABLE ENERGY AND ENERGY CONSERVATION
- Axis
- Asse II Efficienza energetica ed ottimizzazione del sistema
- Operational objective
- Sostenere interventi di efficientamento energetico nell'ambito di azioni integrate di sviluppo urbano sostenibile.
Other projects in territory
Same theme
Same type of investment
LAVORI DI ADEGUAMENTO DELL'IMPIANTO ESISTENTE DEL COMUNE DI CRUCOLI | € 100,000 |
RIPRISTINO TRATTI RETE FOGNARIA FRAZIONE TORRETTA - COMUNE DI CRUCOLI | € 24,050 |