Updated on 30/04/2025
Funding monitored € 186,253.68 of which cohesion funds € 170,422.12
Given name Amount
Development and Cohesion Fund170422.12
Status: other measures15831.56
Economies:
€ 13,746.32
Payments monitored € 186,253.68 of which cohesion funds € 182,575.38
Year Amount Cumulative amount Percentage on public financing
20122468.402468.401
201310623.3713091.777
2014013091.777
2015013091.777
2016013091.777
2017013091.777
2018013091.777
2019173161.91186253.68100

State of progress

Completed
Expected start: 14/10/2014
Effective start: 14/10/2014
Expected end: 19/04/2017
Effective end: 19/04/2017

Type

Theme

  • Environment
  • Altre misure per tutelare l'ambiente e prevenire i rischi

Territory

Entities

Planning body
MINISTERO DELL'AMBIENTE E DELLA SICUREZZA ENERGETICA
Implementing body
COMMISSARIO STRAORDINARIO DELEGATO ALL¿ATTUAZIONE DEGLI INTERVENTI DI MITIGAZIONE DEL RISCHIO IDROGEOLOGICO DI CUI ALL¿ACCORDO DI PROGRAMMA TRA IL MINISTERO DELL¿AMBIENTE E DELLA TUTELA DEL TERRITORIO E DEL MARE E LA REGIONE PIEMONTE (D.P.C.M. 19 APRILE 2011)
Beneficiary
COMUNE DI REVELLO
Executor
COMUNE DI REVELLO
Priority QSN
Energia e ambiente: uso sostenibile e efficiente delle risorse per lo sviluppo
General objective QSN
Garantire le condizioni di sostenibilità ambientale dello sviluppo e livelli adeguati di servizi ambientali per la popolazione e le imprese
Specific objective QSN
Accrescere la capacità di offerta, la qualità e l'efficienza del servizio idrico, e rafforzare la difesa del suolo e la prevenzione dei rischi naturali

Programming area

Programme
PROGRAMMA NAZIONALE DI ATTUAZIONE (PNA) FSC RISANAMENTO AMBIENTALE
2007-2013 National Development and Cohesion Fund
2007-2013 National Development and Cohesion Fund
Cohesion funds
€ 170,422.12
Payments on cohesion funds
€ 182,575.38
Line
Interventi di risanamento ambientale Regione Piemonte
Action
AP per la mitigazione del rischio idrogeologico Regione Piemonte

Other projects in territory