Updated on 30/04/2025
Funding monitored € 359,752.20 of which cohesion funds € 329,173.26
Given name Amount
Development and Cohesion Fund329173.26
Status: other measures30578.94
Economies:
€ 20,247.80
Payments monitored € 359,752.20 of which cohesion funds € 331,335.30
Year Amount Cumulative amount Percentage on public financing
201212100.0012100.003
2013169064.23181164.2350
2014178587.97359752.20100

State of progress

Completed
Expected start: 29/04/2013
Effective start: 29/04/2013
Expected end: 07/06/2013
Effective end: 07/06/2013

Type

Theme

  • Environment
  • Altre misure per tutelare l'ambiente e prevenire i rischi

Territory

Entities

Planning body
MINISTERO DELL'AMBIENTE E DELLA SICUREZZA ENERGETICA
Implementing body
COMMISSARIO STRAORDINARIO DELEGATO ALL¿ATTUAZIONE DEGLI INTERVENTI DI MITIGAZIONE DEL RISCHIO IDROGEOLOGICO DI CUI ALL¿ACCORDO DI PROGRAMMA TRA IL MINISTERO DELL¿AMBIENTE E DELLA TUTELA DEL TERRITORIO E DEL MARE E LA REGIONE PIEMONTE (D.P.C.M. 19 APRILE 2011)
Beneficiary
COMUNE DI PAMPARATO
Executor
COMUNE DI PAMPARATO
Priority QSN
Energia e ambiente: uso sostenibile e efficiente delle risorse per lo sviluppo
General objective QSN
Garantire le condizioni di sostenibilità ambientale dello sviluppo e livelli adeguati di servizi ambientali per la popolazione e le imprese
Specific objective QSN
Accrescere la capacità di offerta, la qualità e l'efficienza del servizio idrico, e rafforzare la difesa del suolo e la prevenzione dei rischi naturali

Programming area

Programme
PROGRAMMA NAZIONALE DI ATTUAZIONE (PNA) FSC RISANAMENTO AMBIENTALE
2007-2013 National Development and Cohesion Fund
2007-2013 National Development and Cohesion Fund
Cohesion funds
€ 329,173.26
Payments on cohesion funds
€ 331,335.30
Line
Interventi di risanamento ambientale Regione Piemonte
Action
AP per la mitigazione del rischio idrogeologico Regione Piemonte