CUP: F77H15001350001
S.S. 653 - Lavori di M.S. di difesa spondale del corpo stradale del fiume Sinni al km 63+500 e al km 57+300
SUMMARY OF THE PROJECT
S.S. 653 - Lavori di M.S. di difesa spondale del corpo stradale del fiume Sinni al km 63+500 e al km 57+300
Implementation indicator
Estensione in lunghezza
- Target
- 6.20 km
- Achieved
- 6.20 km
Download project
Funding monitored
€ 1,787,623.82
of which cohesion funds
€ 1,787,623.82
Given name | Amount |
---|---|
Development and Cohesion Fund | 1787623.82 |
- Economies:
- € 712,376.18
Payments monitored
€ 1,363,472.71
of which cohesion funds
€ 1,363,472.71
76%
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2017 | 287296.09 | 287296.09 | 16 |
2018 | 1045498.25 | 1332794.34 | 74 |
2019 | 4617.32 | 1337411.66 | 74 |
2020 | 19691.13 | 1357102.79 | 75 |
2021 | 6369.92 | 1363472.71 | 76 |
State of progress
Open
Expected start: 21/08/2017
Effective start: 21/08/2017
Expected end: 14/04/2018
Effective end: 14/04/2018
Entities
- Planning body
- ANAS S.p.A.
- Implementing body
- ANAS S.p.A.
- Beneficiary
- ANAS S.p.A.
Programming area
- Programme
- PSC REGIONE BASILICATA
- 2007-2013 National Development and Cohesion Fund
- 2007-2013 National Development and Cohesion Fund
- Cohesion funds
- € 1,787,623.82
- Payments on cohesion funds
- € 1,363,472.71
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale