Updated on 31/10/2024
Funding monitored € 2,500,000.00 of which cohesion funds € 2,500,000.00
Given name Amount
Development and Cohesion Fund2500000.00
Payments monitored € 275,241.50 of which cohesion funds € 275,241.50
Year Amount Cumulative amount Percentage on public financing
201732611.3532611.351
2018150856.19183467.547
201960869.56244337.109
202023195.16267532.2610
20214684.56272216.8210
20220272216.8210
20230272216.8210
20243024.68275241.5011

State of progress

Open
Expected start: 03/11/2025
Effective start: not available
Expected end: 30/12/2027
Effective end: not available

Type

Theme

Territory

Entities

Planning body
REGIONE BASILICATA
Implementing body
REGIONE BASILICATA
Beneficiary
REGIONE BASILICATA

Programming area

Programme
PSC REGIONE BASILICATA
2014-2020 National Development and Cohesion Fund
2014-2020 National Development and Cohesion Fund
Cohesion funds
€ 2,500,000.00
Payments on cohesion funds
€ 275,241.50
Policy Area
Trasporti e Mobilita'
Sector of intervention
Trasporto stradale

Other projects in territory

Same type of investment

CORRIDOIO STRADALE SALERNO - POTENZA - BARI CON ESTENSIONE DELLA DIRETTRICE BASENTANA: R.A. 05 E SS 407 - LAVORI DI RIQUALIFICAZIONE DELLITINERARIO 2 STRALCIO: 1 LOTTO - STRALCIO C TRONCHI 1+2+3 SS407 LAVORI DI RIQUALIFICAZIONE DELLA PIATTAFORMA STRADALE SULLA TRATTA COMPRESA TRA I KM 52+400 E 64+400 - STRALCI C1 C2 E C3 COMPLETAMENTO € 32,000,000
CORRIDOIO STRADALE SALERNO-POTENZA-BARI CON ESTENSIONE DIRETTRICE BASENTANA: R.A. 05 E SS 407 LAVORI DI RIQUALIFICAZIONE DELL'ITINERARIO - 2° STRALCIO 1° LOTTO - STRALCIO C TRONCHI 1+2+3 - SS 407 - LAVORI DI RIQUALIFICAZIONE DELLA PIATTAFORMA STRADALE SULLA TRATTA COMPRESA TRA I KM 52+400 E 64+400 -STRALCI C1 - C2 - C3 - COMPLETAMENTO € 31,999,960
CORRIDOIO STRADALE SALERNO-POTENZA-BARI CON ESTENSIONE DIRETTRICE BASENTANA: R.A. 05 E SS 407 LAVORI DI RIQUALIFICAZIONE DELL'ITINERARIO - 2° STRALCIO 1° LOTTO - STRALCIO D TRONCHI 1+2+3 - SS 407 - LAVORI DI RIQUALIFICAZIONE DELLA PIATTAFORMA STRADALE SULLA TRATTA COMPRESA TRA I KM 64+400 E 76+400 STRALCIO D1-D2-D3 - COMPLETAMENTO (STRALCIO) € 18,641,946
CORRIDOIO STRADALE SALERNO - POTENZA - BARI CON ESTENSIONE DELLA DIRETTRICE BASENTANA: R.A. 05 E SS 407 - LAVORI DI RIQUALIFICAZIONE DELLITINERARIO 2 STRALCIO: 1 LOTTO - STRALCIO C TRONCHI 1+2 SS407 LAVORI DI RIQUALIFICAZIONE DELLA PIATTAFORMA STRADALE SULLA TRATTA COMPRESA TRA I KM 52+400 E 61+400 - STRALCI C1 E C2 1 INTERVENTO € 9,121,992
CORRIDOIO STRADALE SALERNO-POTENZA-BARI CON ESTENSIONE DIRETTRICE BASENTANA: R.A. 05 E SS 407 LAVORI DI RIQUALIFICAZIONE DELL'ITINERARIO - 2° STRALCIO 1° LOTTO - STRALCIO D TRONCHI 2+3 - SS 407 - LAVORI DI RIQUALIFICAZIONE DELLA PIATTAFORMA STRADALE SULLA TRATTA COMPRESA TRA I KM 68+400 E 76+400 STRALCIO D2-D3 - 1° INTERVENTO € 8,179,726