CUP: E46B04000040001
'Paese Albergo Infrastrutture'- realizzazione di infrastrutture per la ricettiviti del centro termale Paese Albergo. II Lotto
SUMMARY OF THE PROJECT
'Paese Albergo Infrastrutture'- realizzazione di infrastrutture per la ricettiviti del centro termale Paese Albergo. II Lotto
Implementation indicator
Non richesto (Migrazione PSC)
- Target
- 0.01 num
- Achieved
- 0.01 num
Download project
Funding monitored
€ 768,688.08
of which cohesion funds
€ 691,819.27
Given name | Amount |
---|---|
Development and Cohesion Fund | 691819.27 |
Municipality | 76868.81 |
Payments monitored
€ 768,688.08
of which cohesion funds
€ 691,819.27
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2006 | 730253.68 | 730253.68 | 95 |
2007 | 0 | 730253.68 | 95 |
2008 | 0 | 730253.68 | 95 |
2009 | 0 | 730253.68 | 95 |
2010 | 0 | 730253.68 | 95 |
2011 | 0 | 730253.68 | 95 |
2012 | 0 | 730253.68 | 95 |
2013 | 0 | 730253.68 | 95 |
2014 | 0 | 730253.68 | 95 |
2015 | 0 | 730253.68 | 95 |
2016 | 38434.40 | 768688.08 | 100 |
State of progress
Completed
Expected start: 21/03/2005
Effective start: 21/03/2005
Expected end: 01/11/2006
Effective end: 01/11/2006
Entities
- Planning body
- COMUNE DI VILLAMAINA
- Implementing body
- COMUNE DI VILLAMAINA
- Beneficiary
- COMUNE DI VILLAMAINA
Programming area
- Programme
- PSC CAMPANIA
- Fondo Aree Sottoutilizzate 2000-2006
- 2000-2006 Underutilized Areas Fund
- Cohesion funds
- € 691,819.27
- Payments on cohesion funds
- € 691,819.27
- Policy Area
- Competitivita' Imprese
- Sector of intervention
- Turismo e ospitalita'