CUP: F78I05000020002
PROGETTO ESECUTIVO DI POTENZIAMENTO, RISTRUTTURAZIONE, AMMODERNAMENTO, AMPLIAMENTO E RAZIONALIZZAZIONE DELLA RETE DI DISTRIBUZIONE IDRICA COMUNALE
SUMMARY OF THE PROJECT
PROGETTO ESECUTIVO DI POTENZIAMENTO, RISTRUTTURAZIONE, AMMODERNAMENTO, AMPLIAMENTO E RAZIONALIZZAZIONE DELLA RETE DI DISTRIBUZIONE IDRICA COMUNALE
Download project
Funding monitored
€ 379,836.71
of which cohesion funds
€ 379,836.71
Given name | Amount |
---|---|
Development and Cohesion Fund | 379836.71 |
Payments monitored
€ 379,836.71
of which cohesion funds
€ 379,836.71
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2005 | 133125.11 | 133125.11 | 35 |
2006 | 116783.06 | 249908.17 | 65 |
2007 | 111118.96 | 361027.13 | 95 |
2008 | 0 | 361027.13 | 95 |
2009 | 0 | 361027.13 | 95 |
2010 | 0 | 361027.13 | 95 |
2011 | 0 | 361027.13 | 95 |
2012 | 0 | 361027.13 | 95 |
2013 | 18809.58 | 379836.71 | 100 |
State of progress
Completed
Expected start: 05/01/2005
Effective start: 05/01/2005
Expected end: 11/10/2007
Effective end: 11/10/2007
Entities
- Planning body
- COMUNE DI LIBERI
- Implementing body
- COMUNE DI LIBERI
- Beneficiary
- COMUNE DI LIBERI
Programming area
- Programme
- PSC CAMPANIA
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 379,836.71
- Payments on cohesion funds
- € 379,836.71
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Risorse idriche