CUP: E94H04000270001
PROGETTO ESECUTIVO CANTIERABILE DEI LAVORI DI COMPLETAMENTO DELLA RETE FOGNARIA COMUNALE E DEI RELATIVI IMPIANTI DI DEPURAZIONE
SUMMARY OF THE PROJECT
PROGETTO ESECUTIVO CANTIERABILE DEI LAVORI DI COMPLETAMENTO DELLA RETE FOGNARIA COMUNALE E DEI RELATIVI IMPIANTI DI DEPURAZIONE
Download project
Funding monitored
€ 1,180,788.00
of which cohesion funds
€ 1,180,788.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 1180788.00 |
Payments monitored
€ 1,149,357.04
of which cohesion funds
€ 1,149,357.04
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2005 | 174798.14 | 174798.14 | 14 |
2006 | 464862.37 | 639660.51 | 54 |
2007 | 156133.15 | 795793.66 | 67 |
2008 | 0 | 795793.66 | 67 |
2009 | 0 | 795793.66 | 67 |
2010 | 0 | 795793.66 | 67 |
2011 | 0 | 795793.66 | 67 |
2012 | 0 | 795793.66 | 67 |
2013 | 0 | 795793.66 | 67 |
2014 | 0 | 795793.66 | 67 |
2015 | 0 | 795793.66 | 67 |
2016 | 0 | 795793.66 | 67 |
2017 | 0 | 795793.66 | 67 |
2018 | 0 | 795793.66 | 67 |
2019 | 0 | 795793.66 | 67 |
2020 | 353563.38 | 1149357.04 | 97 |
State of progress
Completed
Expected start: 31/03/2005
Effective start: 31/03/2005
Expected end: 09/06/2009
Effective end: 09/06/2009
Entities
- Planning body
- COMUNE DI MONTEMILETTO
- Implementing body
- COMUNE DI MONTEMILETTO
- Beneficiary
- COMUNE DI MONTEMILETTO
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC CAMPANIA
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Risorse idriche
Other projects in territory
Same theme
Same type of investment
INTERVENTI PER IL RIPRISTINO A FINI TURISTICO-NATURALI DELLA STORICA TRATTA FERROVIARIA AVELLINO ROCCHETTA S .ANTONIO Â I FASE | € 15,000,000 |