CUP: C83D06000170002
Riqualificazione centro storico: pavimentazione-sottoservizi-pubblica illuminazione-arredo urb.
SUMMARY OF THE PROJECT
Riqualificazione centro storico: pavimentazione-sottoservizi-pubblica illuminazione-arredo urb.
Implementation indicator
Superficie oggetto di intervento
- Target
- 1 mq
- Achieved
- 1 mq
Download project
Funding monitored
€ 1,778,694.45
of which cohesion funds
€ 450,821.47
Given name | Amount |
---|---|
European Union | 1327872.98 |
Development and Cohesion Fund | 450821.47 |
Payments monitored
€ 1,778,694.45
of which cohesion funds
€ 450,821.47
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2009 | 694080.73 | 694080.73 | 39 |
2010 | 640712.83 | 1334793.56 | 75 |
2011 | 0 | 1334793.56 | 75 |
2012 | 0 | 1334793.56 | 75 |
2013 | 0 | 1334793.56 | 75 |
2014 | 0 | 1334793.56 | 75 |
2015 | 0 | 1334793.56 | 75 |
2016 | 0 | 1334793.56 | 75 |
2017 | 0 | 1334793.56 | 75 |
2018 | 0 | 1334793.56 | 75 |
2019 | 443900.89 | 1778694.45 | 100 |
State of progress
Completed
Expected start: 30/04/2009
Effective start: 30/04/2009
Expected end: 30/09/2010
Effective end: 31/03/2015
Entities
- Planning body
- COMUNE DI CASELLE IN PITTARI
- Implementing body
- COMUNE DI CASELLE IN PITTARI
- Beneficiary
- COMUNE DI CASELLE IN PITTARI
Programming area
- Programme
- PSC CAMPANIA
- Fondo Aree Sottoutilizzate 2000-2006
- 2000-2006 Underutilized Areas Fund
- Cohesion funds
- € 450,821.47
- Payments on cohesion funds
- € 450,821.47
- Policy Area
- Riqualificazione urbana
- Sector of intervention
- Edilizia e spazi pubblici
Other projects in territory
Same theme
Same type of investment
53-09 Riqualif. c. storico: pav.-sottoservizi-pubblica illuminazi | € 1,781,373 |
ADEGUAMENTO ALLE NORME COVID | € 5,990 |