CUP: F29H12000360001
MANUTENZIONE ALLA VIABILITÃ DI SERVIZIO AIB
Download project
Funding monitored
€ 98,889.10
of which cohesion funds
€ 98,889.10
Given name | Amount |
---|---|
Revolving Fund (Cohesion Action Plan) | 98889.10 |
Payments monitored
€ 98,889.10
of which cohesion funds
€ 98,889.10
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2012 | 84961.76 | 84961.76 | 85 |
2013 | 11868.70 | 96830.46 | 97 |
2014 | 0 | 96830.46 | 97 |
2015 | 0 | 96830.46 | 97 |
2016 | 2058.64 | 98889.10 | 100 |
State of progress
Completed
Expected start: 09/01/2012
Effective start: 09/01/2012
Expected end: 30/10/2012
Effective end: 30/10/2012
Type
- Infrastructure
- MANUTENZIONE STRAORDINARIA
Theme
- Environment
- Altre misure per tutelare l'ambiente e prevenire i rischi
Territory
Entities
- Planning body
- REGIONE CAMPANIA
- Implementing body
- COMUNITA MONTANA PARTENIO-VALLO DI LAURO
- Beneficiary
- COMUNITA MONTANA PARTENIO-VALLO DI LAURO
- Priority QSN
- Valorizzazione delle risorse naturali e culturali per l'attrattività e lo sviluppo
- General objective QSN
- Valorizzare le risorse naturali, culturali e paesaggistiche locali, trasformandole in vantaggio competitivo per aumentare l'attrattività, anche turistica, del territorio, migliorare la qualità della vita dei residenti e promuovere nuove forme di sviluppo economico sostenibile
- Specific objective QSN
- Rafforzare la capacità di conservazione e gestione delle risorse naturali e culturali mediante la cooperazione territoriale
Programming area
- Programme
- PROGRAMMA PAC CAMPANIA
- 2007-2013 Cohesion Action Plan
- 2007-2013 Cohesion Action Plan
- Cohesion funds
- € 98,889.10
- Payments on cohesion funds
- € 98,889.10
- Line
- Nuove Azioni
- Action
- Azioni per dare continuità all'attuazione del Piano Regionale Forestazione