Programma di Adeguamento del trasporto intermodale nelle zone interessate dal fenomeno bradisismico (art.11 della Legge 887/84) Piano Viario - intervento 3 Via Sartania - Lotti 1-2-3
SUMMARY OF THE PROJECT
Programma di Adeguamento del trasporto intermodale nelle zone interessate dal fenomeno bradisismico (art.11 della Legge 887/84) Piano Viario - intervento 3 Via Sartania - Lotti 1-2-3
Implementation indicator
Non richesto (Migrazione PSC)
- Target
- 0.01 num
- Achieved
- 0.01 num
Download project
Funding monitored
€ 59,511,831.17
of which cohesion funds
€ 53,677,589.24
Given name | Amount |
---|---|
Development and Cohesion Fund | 53677589.24 |
Another public source | 5834241.93 |
Payments monitored
€ 50,649,291.60
of which cohesion funds
€ 47,339,922.64
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2005 | 13433773.38 | 13433773.38 | 22 |
2006 | 3563552.60 | 16997325.98 | 28 |
2007 | 3401873.52 | 20399199.50 | 34 |
2008 | 2189962.27 | 22589161.77 | 37 |
2009 | 8135793.87 | 30724955.64 | 51 |
2010 | 2361194.20 | 33086149.84 | 55 |
2011 | 0 | 33086149.84 | 55 |
2012 | 0 | 33086149.84 | 55 |
2013 | 670867.51 | 33757017.35 | 56 |
2014 | 5543434.11 | 39300451.46 | 66 |
2015 | 43401.08 | 39343852.54 | 66 |
2016 | 3037610.28 | 42381462.82 | 71 |
2017 | 1114733.23 | 43496196.05 | 73 |
2018 | 1713195.01 | 45209391.06 | 75 |
2019 | 1093266.65 | 46302657.71 | 77 |
2020 | 3795611.94 | 50098269.65 | 84 |
2021 | 543645.50 | 50641915.15 | 85 |
2022 | 7376.45 | 50649291.60 | 85 |
State of progress
Open
Expected start: 01/10/2002
Effective start: 01/10/2002
Expected end: 28/04/2023
Effective end: not available
Entities
- Planning body
- REGIONE CAMPANIA
- Implementing body
- REGIONE CAMPANIA
- Beneficiary
- REGIONE CAMPANIA
Programming area
- Programme
- PSC CAMPANIA
- Fondo Aree Sottoutilizzate 2000-2006
- 2000-2006 Underutilized Areas Fund
- Cohesion funds
- € 53,677,589.24
- Payments on cohesion funds
- € 47,339,922.64
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale
Other projects in territory
Same theme
Grande Progetto. Completamento Linea 1 della Metropolitana di Napoli | € 1,384,799,846 |
Raddoppio Frasso Telesino - Vitulano | € 892,552,107 |
Itinerario NA-BA, 1^ tratta: Variante alla linea Napoli-Cancello | € 877,315,676 |
Variante Cancello - Napoli | € 848,000,000 |
Sistema della Metropolitana Regionale - Compl. della Linea 6 della Metropolitana | € 766,051,741 |