CUP: I41B07000010003
LAVORI DI COSTRUZIONE DEL VIADOTTO SULLA SS 7 'APPIA' PER L'OTTIMIZZAZIONE DEL COLLEGAMENTO TRA LA SS FONDO VALLE ISCLERO E L'ASSE ATTTREZZATO VALLE CAUDINA-PIANODARDINE
SUMMARY OF THE PROJECT
LAVORI DI COSTRUZIONE DEL VIADOTTO SULLA SS 7 'APPIA' PER L'OTTIMIZZAZIONE DEL COLLEGAMENTO TRA LA SS FONDO VALLE ISCLERO E L'ASSE ATTTREZZATO VALLE CAUDINA-PIANODARDINE
Implementation indicator
Non richesto (Migrazione PSC)
- Target
- 0.01 num
- Achieved
- 0.01 num
This project is eliminated from views and totals because it is a duplicate of the project:
Funding monitored
€ 6,678,283.32
of which cohesion funds
€ 1,396,073.10
Given name | Amount |
---|---|
European Union | 1805987.34 |
Development and Cohesion Fund | 1396073.10 |
Municipality | 295915.51 |
Another public source | 3180307.37 |
Payments monitored
€ 2,393,915.78
of which cohesion funds
€ 500,440.19
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2009 | 940582.71 | 940582.71 | 14 |
2010 | 0 | 940582.71 | 14 |
2011 | 1055470.59 | 1996053.30 | 29 |
2012 | 0 | 1996053.30 | 29 |
2013 | 397862.48 | 2393915.78 | 35 |
State of progress
Open
Expected start: 16/01/2008
Effective start: 16/01/2008
Expected end: 28/09/2010
Effective end: 16/04/2012
Entities
- Planning body
- AMMINISTRAZIONE PROVINCIALE DI BENEVENTO
- Implementing body
- AMMINISTRAZIONE PROVINCIALE DI BENEVENTO
- Beneficiary
- AMMINISTRAZIONE PROVINCIALE DI BENEVENTO
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC CAMPANIA
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale
Other projects in territory
Same theme
PREVENZIONE INCENDI E DISSESTI IDROGEOLOGICI SULLA RETE STRADALE PROVINCIALE | € 218,361 |