CUP: H71B02000210002
S.P. ni 26: Completamento variante S.Cipriano Picentino - Pezzano
SUMMARY OF THE PROJECT
S.P. ni 26: Completamento variante S.Cipriano Picentino - Pezzano
Implementation indicator
Non richesto (Migrazione PSC)
- Target
- 0.01 num
- Achieved
- 0.01 num
Download project
Funding monitored
€ 478,634.28
of which cohesion funds
€ 478,634.28
Given name | Amount |
---|---|
Development and Cohesion Fund | 478634.28 |
Payments monitored
€ 478,634.28
of which cohesion funds
€ 478,634.28
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2005 | 138000.00 | 138000.00 | 28 |
2006 | 273600.00 | 411600.00 | 85 |
2007 | 67034.28 | 478634.28 | 100 |
State of progress
Completed
Expected start: 06/06/2005
Effective start: 06/06/2005
Expected end: 28/09/2006
Effective end: 28/09/2006
Entities
- Planning body
- REGIONE CAMPANIA
- Implementing body
- REGIONE CAMPANIA
- Beneficiary
- REGIONE CAMPANIA
Programming area
- Programme
- PSC CAMPANIA
- Fondo Aree Sottoutilizzate 2000-2006
- 2000-2006 Underutilized Areas Fund
- Cohesion funds
- € 478,634.28
- Payments on cohesion funds
- € 478,634.28
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale