CUP: F14E05000190001
S.P.66 - Torre le Nocelle
SUMMARY OF THE PROJECT
S.P.66 - Torre le Nocelle
Implementation indicator
Estensione in lunghezza
- Target
- 17 km
- Achieved
- 17 km
Download project
Funding monitored
€ 755,176.93
of which cohesion funds
€ 755,176.93
Given name | Amount |
---|---|
Development and Cohesion Fund | 755176.93 |
Payments monitored
€ 710,481.58
of which cohesion funds
€ 710,481.58
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2005 | 539578.80 | 539578.80 | 71 |
2006 | 112425.72 | 652004.52 | 86 |
2007 | 8351.18 | 660355.70 | 87 |
2008 | 0 | 660355.70 | 87 |
2009 | 40351.21 | 700706.91 | 92 |
2010 | 0 | 700706.91 | 92 |
2011 | 0 | 700706.91 | 92 |
2012 | 3430.67 | 704137.58 | 93 |
2013 | 0 | 704137.58 | 93 |
2014 | 0 | 704137.58 | 93 |
2015 | 0 | 704137.58 | 93 |
2016 | 0 | 704137.58 | 93 |
2017 | 0 | 704137.58 | 93 |
2018 | 0 | 704137.58 | 93 |
2019 | 0 | 704137.58 | 93 |
2020 | 0 | 704137.58 | 93 |
2021 | 0 | 704137.58 | 93 |
2022 | 6344.00 | 710481.58 | 94 |
State of progress
Open
Expected start: 26/07/2004
Effective start: 26/07/2004
Expected end: 15/05/2006
Effective end: 15/05/2006
Entities
- Planning body
- REGIONE CAMPANIA
- Implementing body
- REGIONE CAMPANIA
- Beneficiary
- REGIONE CAMPANIA
Programming area
- Programme
- PSC CAMPANIA
- Fondo Aree Sottoutilizzate 2000-2006
- 2000-2006 Underutilized Areas Fund
- Cohesion funds
- € 755,176.93
- Payments on cohesion funds
- € 710,481.58
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale
Other projects in territory
Same theme
Lavori di completamento variante Pietra | € 384,799 |