CUP: J46E11000840005
COMPLETAMENTO DEI LAVORI DI SISTEMAZIONE IDROGEOLOGICA DEL BACINO VALLONE DELL'OLMO NEL COMUNE DI MONTEFORTE IRPINO (AV)
SUMMARY OF THE PROJECT
COMPLETAMENTO DEI LAVORI DI SISTEMAZIONE IDROGEOLOGICA DEL BACINO VALLONE DELL'OLMO NEL COMUNE DI MONTEFORTE IRPINO (AV)
Download project
Funding monitored
€ 1,056,979.65
of which cohesion funds
€ 1,056,979.65
Given name | Amount |
---|---|
Development and Cohesion Fund | 1056979.65 |
- Economies:
- € 43,020.35
Payments monitored
€ 745,733.20
of which cohesion funds
€ 745,733.20
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2015 | 6770.96 | 6770.96 | 0 |
2016 | 738962.24 | 745733.20 | 70 |
State of progress
Open
Expected start: 10/12/2013
Effective start: 20/03/2017
Expected end: 03/08/2015
Effective end: 02/12/2019
Entities
- Planning body
- COMUNE DI MONTEFORTE IRPINO
- Implementing body
- COMUNE DI MONTEFORTE IRPINO
- Beneficiary
- COMUNE DI MONTEFORTE IRPINO
Programming area
- Programme
- PSC CAMPANIA
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 1,056,979.65
- Payments on cohesion funds
- € 745,733.20
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico