CUP: D58C07000100002
(MONDRAGONE) REDAZIONE PROGRAMMA INTEGRATO
SUMMARY OF THE PROJECT
(MONDRAGONE) REDAZIONE PROGRAMMA INTEGRATO
Implementation indicator
Non richesto (Migrazione PSC)
- Target
- 0.01 num
- Achieved
- 0.01 num
Funding monitored
€ 99,750.00
of which cohesion funds
€ 66,500.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 66500.00 |
Municipality | 33250.00 |
- Economies:
- € 33,250.00
Payments monitored
€ 99,750.00
of which cohesion funds
€ 55,416.67
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2007 | 83125.00 | 83125.00 | 83 |
2008 | 0 | 83125.00 | 83 |
2009 | 0 | 83125.00 | 83 |
2010 | 0 | 83125.00 | 83 |
2011 | 0 | 83125.00 | 83 |
2012 | 0 | 83125.00 | 83 |
2013 | 0 | 83125.00 | 83 |
2014 | 0 | 83125.00 | 83 |
2015 | 0 | 83125.00 | 83 |
2016 | 0 | 83125.00 | 83 |
2017 | 0 | 83125.00 | 83 |
2018 | 0 | 83125.00 | 83 |
2019 | 0 | 83125.00 | 83 |
2020 | 16625.00 | 99750.00 | 100 |
State of progress
Completed
Expected start: 10/09/2006
Effective start: 10/09/2006
Expected end: 15/10/2013
Effective end: 15/10/2013
Entities
- Planning body
- REGIONE CAMPANIA
- Implementing body
- REGIONE CAMPANIA
- Beneficiary
- REGIONE CAMPANIA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC CAMPANIA
- Policy Area
- Cultura
- Sector of intervention
- Patrimonio e paesaggio